User login

Maintenance History

Equipment Date(y-m-d)sort ascending
Synopsis
Image Attachment Document Author
Maintenance for DRP-03 2023-12-06 Factory refurbished pump head installed. Deepak Vyas
Maintenance for DRP-35 2023-11-30 Pump module exchanged for a factory rebuilt one. Deepak Vyas
Maintenance for DR(Pandora) 2023-11-22 Penning gauge reading too high!-Clean oil for Diff Pump Bassam Hitti
Maintenance for M15 2023-11-14 Replacement S1DP1 Separator diffusion pumps heater . , , , , Rahim Abasalti
Maintenance for OLP-04 2023-10-14 Oil changed on this pump installed on the leak detector. Deepak Vyas
Maintenance for OLP-09 2023-10-14 Oil changed on pump which is typically used on the vacuum oven in the mezzanine. Deepak Vyas
Maintenance for DRP-35 2023-09-25 Pump module exchanged for a factory rebuilt one. Deepak Vyas
Maintenance for BNQR Cryostat 2023-07-19 Modification on "Second Version" of Al Heat Shield Flange Rahim Abasalti
Maintenance for BNQR Cryostat 2023-07-19 Thermometers Replacement Rahim Abasalti
Maintenance for BNQR Cryostat 2023-06-13 He leak into UHV Gerald Morris
Maintenance for M9A 2023-06-06 SO2 Purity in Separators SF6 Volumes Rahim Abasalti
Maintenance for SF6 Aciditor 2023-05-31 SO2 Sensor Replacement
  1. AttachmentSize
    PDF icon eurogas125444.pdf1.31 MB
Rahim Abasalti
Maintenance for M20 Upstream 2023-05-22 M20 IG controllers' cards repaired Gerald Morris
Maintenance for M20 Upstream 2023-05-08 Ion gauge filaments and Window materials changed. Deepak Vyas
Maintenance for M9A 2023-03-29 Separator 1- Ion Gauge Addition Rahim Abasalti
Maintenance for M9A 2023-03-23 Separator 2- Addition & Replacement Ion Gauges , Rahim Abasalti
Maintenance for OMF-04 2023-03-20 Replaces with OMF-06 Rahim Abasalti
Maintenance for M15 2023-03-10 Separator 1 Positive and Negative Feedthrough Replacement Darren Blom
Maintenance for M20 Upstream 2023-03-06 Log of recent maintenance on M20. Gerald Morris
Maintenance for M20 Upstream 2023-03-06 M20 turbo pumps. Gerald Morris
Maintenance for ISAC-1 BNMR 2023-02-24 All scroll pumps tested to determine base pressure, state of wear. Cold start of all bNQR, bNMR scroll pumps and initial pumpdown., base pressures after severla days running. Gerald Morris
Maintenance for M20 Upstream 2023-02-23 SF6 gas cylinder changed. Gerald Morris
Maintenance for M20 Upstream 2023-02-17 Leak observed and diagnosed and remedied. , , , , Rahim Abasalti
Maintenance for DR(Pandora) 2023-02-17 Leak into OVC, short internal z-coil and leaky Auto V12 , , , , , , , Bassam Hitti
Maintenance for ISAC-1 BNMR 2023-02-17 beta-NMR isolation transformer leaky input feedthrough is repaired Gerald Morris
Maintenance for ISAC-I BNQR 2022-09-23 TP ILE2A1:TP1 failed & replaced
  1. AttachmentSize
    PDF icon Turbo pump ILE2A1:TP1 replacement379.17 KB
Gerald Morris
Maintenance for DRP-23 2022-06-09 Pump module changed. Deepak Vyas
Maintenance for DRP-02 2022-06-09 Pump module changed. Deepak Vyas
Maintenance for DRP-50 2022-04-28 Tip seals changed. Deepak Vyas
Maintenance for DRP-50 2022-04-28 Tip seals changed. Deepak Vyas
Maintenance for DRP-50 2022-04-27 Tip seals changed. Deepak Vyas
Maintenance for DRP-19 2022-04-27 VPI replaced. Deepak Vyas
Maintenance for DRP-18 2022-04-27 VPI Solenoid changed. Deepak Vyas
Maintenance for DRP-41 2022-04-27 VPI Solenoid changed. Deepak Vyas
Maintenance for DR(Pandora) 2022-03-03 Leak in GHS Rahim Abasalti
Maintenance for DR(Pandora) 2022-02-18 Adjust the mixture pressure and He3/He4 ratio Bassam Hitti
Maintenance for DR(Pandora) 2022-01-21 Replacement and Maintenance of 1Kpot and Diff Pump Valves Rahim Abasalti
Maintenance for DR(Pandora) 2022-01-19 Installation of Automated Flow Controller valve
  1. AttachmentSize
    PDF icon mnl_DR_ASCO_FlowValve_8290_r5.pdf1.35 MB
Rahim Abasalti
Maintenance for DR(Pandora) 2022-01-17 Installation: New SS Tubing for GHS, Minature Gate valve Rahim Abasalti
Maintenance for M15 2021-11-09 Replace Bad O-Ring on Separator 1 Upstream Window Valve Pinched O-Ring ID 7.984 X 0.139 W Darren Blom
Maintenance for DRP-13 2021-10-28 Removed from service. Anomolous puff of air. Deepak Vyas
Maintenance for CRP-06 2021-10-28 Taken out of service Deepak Vyas
Maintenance for CRP-02 2021-10-28 Rebuild Deepak Vyas
Maintenance for DRP-50 2021-10-28 Removed from service. Deepak Vyas
Maintenance for DRP-20 2021-10-28 VPI valve failure Deepak Vyas
Maintenance for TPS-C1 2021-10-28 Gauge cleaned Deepak Vyas
Maintenance for CRP-13 2021-10-28 Puff of air. Deepak Vyas
Maintenance for DRP-35 2021-10-19 Tip Seals changed Deepak Vyas
Maintenance for TPS-C1 2021-10-19 Tip Seals changed Deepak Vyas
Maintenance for M15 2021-10-19 Replaced Sep. 2 Ion Gauge Wiring Config for Ion Gauge, Replacement  Ion Gauge Darren Blom
Maintenance for CRP-07 2021-10-12 Rebuild, motor change and crankshaft and eccentric changed. Deepak Vyas
Maintenance for CRP-11 2021-10-12 Rebuilt cold head, New arrays. Deepak Vyas
Maintenance for CRP-04 2021-10-12 Rebuild and motor change. Deepak Vyas
Maintenance for DRP-05 2021-08-17 Factory full rebuild. Deepak Vyas
Maintenance for TPS-C3 2021-08-17 Gauge cleaned Deepak Vyas
Maintenance for TPS-C5 2021-08-17 Gauge cleaned and Tipseals changed Deepak Vyas
Maintenance for Horizontal Gas Flow Cryostat 2 2021-08-16 Leaky Window Replacement , , , , , , , , , Rahim Abasalti
Maintenance for TPS-C2 2021-08-16 Gauge cleaned and Tipseals changed Deepak Vyas
Maintenance for DRP-38 2021-07-08 Scroll surface failure. Deepak Vyas
Maintenance for M15 2021-04-20 S1DP1 Separator diffusion pumps heater refreshed. Deepak Vyas
Maintenance for M15 2021-04-14 S2DP1 Separator diff pump heater checked. Deepak Vyas
Maintenance for M15 2021-03-29 All three window valves membranes changed. Deepak Vyas
Maintenance for M20C 2021-03-19 Separator windows changed. Deepak Vyas
Maintenance for CPC-10 2021-03-16 Adsorber Changed Deepak Vyas
Maintenance for CMP-04 2021-03-16 Adsorber Changed Deepak Vyas
Maintenance for DRP-06 2021-03-12 Decommissioned and disposed. Deepak Vyas
Maintenance for Cobra-01 2021-03-12 CSA Certification
  1. AttachmentSize
    PDF icon Cobra_BA 0100C_CSA_Certification.pdf610.14 KB
Rahim Abasalti
Maintenance for M15 2021-03-05 Fix the Argon flow Piezo-electric valve (Separator 1). Bassam Hitti
Maintenance for CRP-10 2020-11-19 Rebuild Deepak Vyas
Maintenance for M9A 2020-10-26 Replacing pressure switch for S2, Negative on Stack Volume Rahim Abasalti
Maintenance for Gas Flow Cryostat (Miss Piggy) 2020-01-30 Replace the temperature sensor on the window heater and Needle Valve O-rings. , Bassam Hitti
Maintenance for TPS-C4 2019-12-24 Tip seal reset 6492 hrs. Deepak Vyas
Maintenance for TPS-C4 2019-12-19 Tip Seals changed. Rahim Abasalti
Maintenance for TPS-C4 2019-12-18 All in one gauge cleaned. Deepak Vyas
Maintenance for TPS-C5 2019-12-18 All in one gauge cleaned. Deepak Vyas
Maintenance for TPS-C1 2019-12-18 All in one gauge cleaned. Deepak Vyas
Maintenance for TPS-C2 2019-12-18 All in one gauge cleaned. Deepak Vyas
Maintenance for bNQR Cryo Oven 2019-10-10 Upgraded Capacity to 523K and thermometery Rahim Abasalti
Maintenance for BNMR-Oxford Cryostat 2019-10-07 High-T Upgrade Finished , , , , , , , , Derek Fujimoto
Maintenance for bNQR Cryo Oven 2019-10-02 Pre-beam bake and RGA , , , , , , Derek Fujimoto
Maintenance for BNMR-Oxford Cryostat 2019-09-19 High-T Upgrade Started , , , Derek Fujimoto
Maintenance for DRP-10 2019-07-29 Contoller box exchanged. Deepak Vyas
Maintenance for DRP-03 2019-06-19 Motor swap Deepak Vyas
Maintenance for DRP46 2019-06-19 Motor swap Deepak Vyas
Maintenance for DRP46 2019-06-18 Tip Seals changed. Deepak Vyas
Maintenance for CMP-06 2019-06-14 Helium gas exchanged. Deepak Vyas
Maintenance for CMP-07 2019-06-14 Helium gas exchanged. Deepak Vyas
Maintenance for CMP-11 2019-06-14 BNMR:CP5 : Adsorber changed. Deepak Vyas
Maintenance for CMP-08 2019-06-14 Helium gas exchanged. Deepak Vyas
Maintenance for CMP-11 2019-06-13 BNMR:CP5 : Adsorber changed. Deepak Vyas
Maintenance for DR(Pandora) 2019-06-12 Helium gas leak from dilution unit into IVC , Bassam Hitti
Maintenance for DR(Pandora) 2019-06-12 VSU DR top loading siphon modified to use with Pandora Bassam Hitti
Maintenance for DR(Pandora) 2019-06-11 Valved Liquid Helium Transfer-line being Repaired. Deepak Vyas
Maintenance for Helios 2019-06-07 Transfer line leaks , , Deepak Vyas
Maintenance for CRP-01 2019-04-26 Cold head changed. Deepak Vyas
Maintenance for DR(Pandora) 2019-04-25 Large MuSR copper background Bassam Hitti
Maintenance for M15 2019-04-20 Sep1 POS SF6 Leaking Bassam Hitti
Maintenance for M20D 2019-04-16 O-ring on slits leaking , , , , Deepak Vyas
Maintenance for OLP-04 2019-04-09 Oil changed. Deepak Vyas
Maintenance for OLP-06 2019-04-02 Oil Changed. Deepak Vyas
Maintenance for OLP-09 2019-04-02 Oil Changed. Deepak Vyas
Maintenance for OLP-03 2019-04-01 Oil changed and installed on DR Deepak Vyas
Maintenance for OLP-21 2019-04-01 Oil changed Deepak Vyas
Maintenance for DRP-22 2019-03-26 Pump installed under septum in M20 Rahim Abasalti
Maintenance for DRP-34 2019-03-26 Pump removed from Service. Rahim Abasalti
Maintenance for CMP-01 2019-03-01 Adsorber changed. Deepak Vyas
Maintenance for Gas Flow Cryostat (Miss Piggy) 2019-02-06 Fix of the helium leak into the cryostat vacuum at base temperature. , , Bassam Hitti
Maintenance for OLP-04 2019-01-30 Oil changed. Deepak Vyas
Maintenance for OLP-18 2019-01-14 Oil Change Rahim Abasalti
Maintenance for DR(Pandora) 2019-01-14 General Maintenance Rahim Abasalti
Maintenance for DRP-17 2018-12-12 Pump found dead and marked dead. 7007 hrs Deepak Vyas
Maintenance for TPS-C1 2018-11-26 Replacement Faulty Board Rahim Abasalti
Maintenance for Gas Flow Cryostat (Miss Piggy) 2018-10-11 Helium leak into the cryostat vacuum at base temperature. Bassam Hitti
Maintenance for CRP-09 2018-09-18 Rebuild and Reinstall Deepak Vyas
Maintenance for ISAC-I BNQR 2018-07-05 installation Seal-Kit for Load Lock 2" Gate Valve , ,
  1. AttachmentSize
    PDF icon vat_2_75_gate-Valve.pdf590.03 KB
Rahim Abasalti
Maintenance for DR(Pandora) 2018-06-05 Replacing Threaded Copper piece on Sample Siphon , , Rahim Abasalti
Maintenance for CMP13 2018-04-13 Installation Deepak Vyas
Maintenance for DRP-43 2018-04-13 Hour Meter,Electrical Box, Pump Fluid Rahim Abasalti
Maintenance for DRP-42 2018-04-12 Hour Meter,Electrical Box, Pump Fluid Rahim Abasalti
Maintenance for DRP-04 2018-04-04 Full Rebuild Deepak Vyas
Maintenance for M15 2018-03-21 Replace leaky O-ring seals for the valve (VA1) and window (AW1) between the M15 experimental area and Separator 2. Bassam Hitti
Maintenance for M15 2018-03-21 Summary of Steve Dunbar's work between 2005 and 2014. Bassam Hitti
Maintenance for DRP-17 2018-01-26 Pump Run to maintain it's operation. Deepak Vyas
Maintenance for BNQR Cryostat 2017-11-24 Thermometers not working Rahim Abasalti
Maintenance for DRP-04 2017-10-23 Motor swap! Deepak Vyas
Maintenance for DRP-23 2017-10-23 Motor swap! Deepak Vyas
Maintenance for TPS-C1 2017-10-18 Tip Seal replacement (premature) 1661 HRS Deepak Vyas
Maintenance for DRP-08 2017-10-18 STANDARD OVERHAUL
  1. AttachmentSize
    PDF icon Repair Estimate Quote74.47 KB
Rahim Abasalti
Maintenance for DRP-34 2017-10-17 Tip seal replacement. Deepak Vyas
Maintenance for DRP-34 2017-10-16 Tip Seals Changed Deepak Vyas
Maintenance for DRP-02 2017-10-08 Full rebuild Deepak Vyas
Maintenance for DRP-05 2017-10-08 Full rebuild Deepak Vyas
Maintenance for DRP-02 2017-09-29 Tip Seals Changed Deepak Vyas
Maintenance for DRP-04 2017-09-18 Tip Seal replacement Deepak Vyas
Maintenance for DRP-39 2017-09-15 Major Rebuild Deepak Vyas
Maintenance for CMP-11 2017-07-07 Installation Description Deepak Vyas
Maintenance for CMP-04 2017-06-23 Compressor removed from service at BNMR cage location (ILE2A3CP5) Deepak Vyas
Maintenance for SF6 Aciditor 2017-04-03 SO2 Sensor Replacement
  1. AttachmentSize
    PDF icon Sensor_Certificate_wika125525.pdf415.3 KB
Rahim Abasalti
Maintenance for CPC-10 2017-03-29 Compressor unit failed. 10449hrs Deepak Vyas
Maintenance for CMP-05 2017-03-29 Adsorber update. Deepak Vyas
Maintenance for CRP-01 2017-03-29 Aluminum Tape failed and was changed. Deepak Vyas
Maintenance for CRP-02 2017-03-29 Helium Charged. Deepak Vyas
Maintenance for CMP-01 2017-03-29 Adsorber update. Deepak Vyas
Maintenance for DRP-07 2017-03-17 STANDARD OVERHAUL
  1. AttachmentSize
    PDF icon Repair Estimate Quote72.66 KB
Rahim Abasalti
Maintenance for DRP-17 2017-03-16 STANDARD OVERHAUL Rahim Abasalti
Maintenance for DRP-15 2017-03-16 STANDARD OVERHAUL Rahim Abasalti
Maintenance for SF6 Gas Reclaimer 2017-02-09 System Filters changed, compressors tested and System evacuated. Deepak Vyas
Maintenance for DRP-04 2016-11-29 Full rebuild Deepak Vyas
Maintenance for DRP-03 2016-11-29 Full rebuild Deepak Vyas
Maintenance for TPS-C1 2016-10-06 Tip Seals changed and hours reset 5124 hours on original Tip Seals. Deepak Vyas
Maintenance for TPS-C2 2016-10-04 Tip Seals changed and hours reset 7803 hours on original Tip Seals. Deepak Vyas
Maintenance for TPS-C3 2016-10-03 Tip Seals changed and hours reset 4407 hours on original Tip Seals. Deepak Vyas
Maintenance for TPS-C5 2016-09-29 Tip Seal hours reset. Deepak Vyas
Maintenance for TPS-C5 2016-09-28 Tip Seal Replacement. Deepak Vyas
Maintenance for SF6 Gas Reclaimer 2016-09-15 Vacuum pump oil change Deepak Vyas
Maintenance for OLP-04 2016-09-02 Oil Changed. Deepak Vyas
Maintenance for M15 2016-08-25 M15 Separator 1 Negative Feed Through Removal and Replacement Darren Blom
Maintenance for DRP-23 2016-05-31 Major Rebuild Deepak Vyas
Maintenance for OLP-18 2016-04-25 Added Two Gate Valves, Hour-meter, And Thermometer Sticker Rahim Abasalti
Maintenance for Horizontal Gas Flow Cryostat 2 2016-04-05 Shielding of the applied magnetic field at low temperature.
  1. AttachmentSize
    PDF icon Fix387.42 KB
Bassam Hitti
Maintenance for OLP-10 2016-03-10 Pump Tested OK Deepak Vyas
Maintenance for BNMR-Oxford Cryostat 2016-02-23 Bellows drive bearings changed. Deepak Vyas
Maintenance for BNMR-Oxford Cryostat 2016-02-10 Bearings removed on horizontal linear cryostat translator. Deepak Vyas
Maintenance for BNQR Cryostat 2016-01-26 Repair Helium Leak in Heat Exchanger , , , , , , , , , Rahim Abasalti
Maintenance for OLP-18 2015-11-24 Repair on Pump , Before disassemble the pump, Before disassemble the pump, side view, Before disassemble the pump, top view, Oil pump(item #42) removed, item #5, Intermediate flange, item #5, Intermediate flange, Item #7, Rear flange, item #1, Front plate, Debries on Rotor(item #16) Rahim Abasalti
Maintenance for DR(Pandora) 2015-11-24 Exchangeing He3 rotary Vane Pump and Coalescing Filter Rahim Abasalti
Maintenance for CMP-03 2015-09-29 Rebuilt cryopump installed and adsorber changed.. Deepak Vyas
Maintenance for BNMR-Oxford Cryostat 2015-09-28 Installation of back Scatter plate Rahim Abasalti
Maintenance for DR(Pandora) 2015-09-24 Maintenance on Top Loading Siphon , Rahim Abasalti
Maintenance for DRP-23 2015-09-20 Sounded Horrible Deepak Vyas
Maintenance for ISAC-1 BNMR 2015-07-14 Cleaning the 10-inch Ceramic Break , , , , , , , , , Rahim Abasalti, Gerald Morris
Maintenance for BNMR-Oxford Cryostat 2015-04-29 Unmouting Back-Scatter Plate Rahim Abasalti
Maintenance for M15 2015-04-25 Replace old quadrupole magnets power supplies
  1. AttachmentSize
    PDF icon Quad Power Supplies92.9 KB
Bassam Hitti
Maintenance for BNMR-Oxford Cryostat 2015-04-02 Back-Scatter Plate Added , , , Rahim Abasalti
Maintenance for CMP-05 2015-03-26 Pressure adjusted BNMR-CP4 Deepak Vyas
Maintenance for CMP-04 2015-03-26 Pressure adjusted BNMR-CP5 Deepak Vyas
Maintenance for CMP-08 2015-03-25 Adsorber changed ILE2A1-CP3 Deepak Vyas
Maintenance for CMP-07 2015-03-24 Pressure adjusted BNMR-CP3 Deepak Vyas
Maintenance for CMP-06 2015-03-24 Adsorber changed ILE2A3-CP2 Deepak Vyas
Maintenance for M15 2015-03-06 M15 Separator 1 Negative Feed Through Removal and Replacement Darren Blom
Maintenance for OLP-09 2015-02-20 Pump Rebuilt Deepak Vyas
Maintenance for OLP-05 2015-02-10 Pump Rebuilt Deepak Vyas
Maintenance for ThermoHaake 2014-10-27 Hose rewelded and redressed Deepak Vyas
Maintenance for OLP-01 2014-10-15 Pump Temporarily Decommisioned Deepak Vyas
Maintenance for OLP-02 2014-10-15 Pump Temporarily Decommisioned Deepak Vyas
Maintenance for OLP-07 2014-10-15 Pump Temporarily Decommisioned Deepak Vyas
Maintenance for OLP-06 2014-05-01 Oil changed Deepak Vyas
Maintenance for OLP-08 2014-05-01 Oil changed Deepak Vyas
Maintenance for CP-05 2014-04-30 Pump serviced Deepak Vyas
Maintenance for DRP-02 2014-03-06 Pump serviced Deepak Vyas
Maintenance for CP-11 2014-02-13 C-clip failed and subsequent operation caused failure. Deepak Vyas
Maintenance for CP-11 2014-02-13 Pump rebuilt. Deepak Vyas
Maintenance for CRP-02 2014-02-13 Full rebuild Deepak Vyas
Maintenance for CP-01 2013-06-06 Removed from service from M20 Separator 1 Deepak Vyas
Maintenance for OLP-03 2013-05-17 Oil changed Deepak Vyas
Maintenance for OLP-06 2013-05-17 Oil changed and flushed Deepak Vyas
Maintenance for OLP-01 2013-05-17 Oil changed Deepak Vyas
Maintenance for CPC-09 2013-05-15 Adsorber changed @ 10264HRS Deepak Vyas
Maintenance for TRP-06 2013-05-13 Not working. Sent out for rebuilding. Gerald Morris
Maintenance for DRP-06 2013-05-09 Tip seals replaced. Deepak Vyas
Maintenance for CRP-01 2013-04-30 Full rebuild Deepak Vyas
Maintenance for TRP-04 2013-04-12 Fan Changed Gerald Morris
Maintenance for TRP-05 2013-04-12 Fan Changed Gerald Morris
Maintenance for TRP-08 2013-03-28 Installation Gerald Morris
Maintenance for TRP-08 2013-03-28 Cooling fan changed. Gerald Morris
Maintenance for Helios 2013-03-06 Liquid Nitrogen Auto Fill System Bassam Hitti
Maintenance for DR 2013-03-05 Replace top flange O-ring , , Damage to the groove Bassam Hitti
Maintenance for DR(Pandora) 2013-02-22 Top Large Flange O-ring Replacement , , , , , , , , , Rahim Abasalti
Maintenance for DR(Pandora) 2013-01-15 DR check after warm up Bassam Hitti
Maintenance for DR(Pandora) 2012-09-28 increase in L-He consumption/ condensation on vacuum jacket Bassam Hitti
Maintenance for BNMR-Oxford 2012-09-14 Gold Plating the Copper Disk , Rahim Abasalti
Maintenance for BNMR-Oxford Cryostat 2012-09-14 Gold Plated Cryostat Cap , , , , Rahim Abasalti
Maintenance for M9B 2012-09-12 Patching Up Solenoid Gas Cooled Lead Flanges Leak , , , , , , Rahim Abasalti
Maintenance for M15 2012-07-31 spin rotators HV+ suppplies recover poorly after being shut down for several hours Syd Kreitzman
Maintenance for OLP-04 2012-07-16 Oil change Deepak Vyas
Maintenance for OLP-20 2012-07-16 Oil change Deepak Vyas
Maintenance for DR(Pandora) 2012-07-10 Leak from dilution unit to IVC
  1. AttachmentSize
    PDF icon DR leak region.pdf119.77 KB
Bassam Hitti
Maintenance for M9B 2012-03-30 Beam Height adjustment Rahim Abasalti
Maintenance for OLP-11 2012-02-08 Oil changed Deepak Vyas
Maintenance for DR(Pandora) 2011-10-03 Aire Minature Pressure Switch
  1. AttachmentSize
    PDF icon mnl_air_pressure_switch.pdf498.96 KB
    PDF icon pressure_switch_spec.pdf233.17 KB
Rahim Abasalti
Maintenance for ThermoHaake 2011-04-26 Replacement unit Donald Arsenau
Maintenance for Circulator 2011-04-26 Replacement Unit Donald Arsenau
Maintenance for BNMR-Oxford Cryostat 2010-05-19 Leak Repair Rahim Abasalti
Maintenance for Horizontal Gas Flow Cryostat 1 2010-04-19 Weak magnetism at low temperature Bassam Hitti
Maintenance for DR(Pandora) 2009-12-12 XGS-600 Gauge Controller Replacement Rahim Abasalti
Maintenance for HGFC-Oxford 2009-10-31 Repair Leak in Vacuum and Helium Space Rahim Abasalti, Bassam Hitti
Maintenance for OLP-08 2009-10-16 Case Gasket Deepak Vyas
Maintenance for DR(Pandora) 2009-08-24 QSB Valve Repair Rahim Abasalti
Maintenance for High-Time 2009-07-14 X-Y Table Bellows Replacement Rahim Abasalti
Maintenance for Horizontal Gas Flow Cryostat 1 2009-05-08 Kapton Window Replacement Rahim Abasalti
Maintenance for M9B 2009-03-30 Beam Height adjustment Rahim Abasalti
Maintenance for High-Time 2009-03-26 Field Decay Bassam Hitti
Maintenance for High-Time 2009-03-24 Test Results Bassam Hitti
Maintenance for High-Time 2009-03-23 American Magnetic report Bassam Hitti
Maintenance for High-Time 2009-03-23 Magnet Failure in 2008 Bassam Hitti
Maintenance for DR(Pandora) 2009-02-18 Fixing Broken LN2 Shield Kel-F Spacer and Installing New Ones , , Rahim Abasalti
Maintenance for DR(Pandora) 2009-01-22 Reinstallation Booster Pump Rahim Abasalti
Maintenance for DR(Pandora) 2008-11-24 Magnet Spacer(Kel-F) Replacement Rahim Abasalti
Maintenance for Horizontal Gas Flow Cryostat 1 2008-11-24 Kapton Window Change Rahim Abasalti
Maintenance for OLP-18 2008-11-12 Oil changed After Major Repair Rahim Abasalti
Maintenance for Helios 2008-11-01 Quench!! Rahim Abasalti
Maintenance for ThermoHaake 2008-10-31 Control lock-up Donald Arsenau
Maintenance for Circulator 2008-10-31 Control Lock-up Donald Arsenau
Maintenance for DR(Pandora) 2008-10-06 Gas Analyzer- O2 Sensor Replacement Rahim Abasalti
Maintenance for Belle 2008-08-13 Leak Check Rahim Abasalti
Maintenance for OLP-18 2008-06-13 Major Repair , Rahim Abasalti
Maintenance for Horizontal Gas Flow Cryostat 1 2008-02-26 Origin of Large Anomalous Knight Shift at Low Temperature Rahim Abasalti, Bassam Hitti
Maintenance for BNQR Cryostat 2008-02-19 Modification on Al Heat Shield Flange Beta-NQR Original Aluminium Shield Modification Rahim Abasalti
Maintenance for OLP-06 2008-02-14 Varian Pump DS302 Put in place of damaged alcatel 2012. Deepak Vyas
Maintenance for OLP-08 2008-02-12 Oil changed Deepak Vyas
Maintenance for OLP-20 2008-02-11 Oil changed Deepak Vyas
Maintenance for OLP-10 2008-02-11 Oil changed Deepak Vyas
Maintenance for OLP-03 2008-02-10 Oil changed Deepak Vyas
Maintenance for OLP-04 2008-02-04 Oil changed Deepak Vyas
Maintenance for OLP-01 2008-01-15 Pump Service Deepak Vyas
Maintenance for Belle 2007-11-22 Removing Magnet and Some Notes Rahim Abasalti
Maintenance for Horizontal Gas Flow Cryostat 2 2007-09-27 Repair and Diode Replacement Rahim Abasalti, Bassam Hitti
Maintenance for DR(Pandora) 2007-09-05 Side Pocket Replacement Deepak Vyas
Maintenance for DR(Pandora) 2007-06-04 Heat Exchanger Repair Rahim Abasalti
Maintenance for DR(Pandora) 2007-02-07 Gas Analyzer- O2 Sensor Replacement Rahim Abasalti
Maintenance for Helios 2007-02-07 Modifying N2 Sensor Rahim Abasalti
Maintenance for Varian979 2007-01-23 maintaining spectrometer tube assembly , , , , , , Rahim Abasalti
Maintenance for OLP-04 2007-01-23 Oil changed and LD serviced Rahim Abasalti
Maintenance for Helios 2007-01-22 Fixing Vacuum Jacket Indium Seal Leak Rahim Abasalti
Maintenance for DR(Pandora) 2007-01-17 Cleaning Gauges, Valves, and Gas Handeling Lines Rahim Abasalti
Maintenance for Helios 2006-09-11 Cold Cathode Gauge Maintenance Rahim Abasalti
Maintenance for DR(Pandora) 2006-08-10 Flow Through Test and Leak Check Rahim Abasalti
Maintenance for OLP-20 2006-08-09 Oil changed Rahim Abasalti
Maintenance for OLP-10 2006-08-09 Oil changed Rahim Abasalti
Maintenance for OLP-18 2006-04-26 Oil Changed Rahim Abasalti
Maintenance for Helios 2006-04-19
Maintenance for BNMR-Oxford Cryostat 2005-08-09 Kapton Heater Rahim Abasalti
Maintenance for Helios 2005-05-18 Temp Results After Taping Magnet Rahim Abasalti
Maintenance for OLP-04 2005-04-27 Oil changed Rahim Abasalti
Maintenance for Helios 2005-04-26 Cooling to He Rahim Abasalti
Maintenance for Helios 2005-04-25 Temp @ N2 Rahim Abasalti
Maintenance for Helios 2005-02-23 Temp Results at LN2 Rahim Abasalti
Maintenance for Helios 2005-02-22 Leak Rate While Cooling Down Rahim Abasalti
Maintenance for Helios 2005-02-08 Modification Top Flange of He Bath Rahim Abasalti
Maintenance for Helios 2005-01-07 Temp Test at SS Neck Rahim Abasalti
Maintenance for DR(Pandora) 2004-11-22 Flow Through Test and Leak Checking IVC/OVC Rahim Abasalti
Maintenance for DR(Pandora) 2004-10-19 Leak Rate While Cooling Down Rahim Abasalti
Maintenance for Varian979 2004-09-29 Oil change Edi Dalla Valle
Maintenance for OLP-04 2004-09-29 Oil changed Rahim Abasalti
Maintenance for DR(Pandora) 2004-09-28 Flow Test and Leak Checking iVC?OVC Rahim Abasalti
Maintenance for Helios 2004-09-12 Leak Rate and Temp While Cooling Down Rahim Abasalti
Maintenance for DR(Pandora) 2004-08-10 Flow Through Test and Leak Checking IVC/OVC Rahim Abasalti
Maintenance for Helios 2004-08-04 Leak Rate @ He Temperature Rahim Abasalti
Maintenance for DR(Pandora) 2004-05-19 Installing Gauges for IVC/OVC Rahim Abasalti
Maintenance for BNMR-Oxford Cryostat 2004-05-05 Burnt Heaters Rahim Abasalti
Maintenance for Helios 2004-04-19 Leak Rate Rahim Abasalti
Maintenance for BNMR-Oxford Cryostat 2003-05-22 Diode and RF Leads Rahim Abasalti
Maintenance for DR(Pandora) 2003-04-28 Filter and Gauge cleaning Rahim Abasalti
Maintenance for BNMR-Oxford Cryostat 2002-04-20 Diode Replacement and Wiring Maintenance Rahim Abasalti
Maintenance for BNMR-Oxford Cryostat 2002-03-01 Diode Replacement Rahim Abasalti