Maintenance for DR(Pandora)

Date: 
Wednesday, September 5, 2007
Synopsis: 
Side Pocket Replacement
Equipment/Beam Line: 
Description: 

Titanium side pockets arrived leak checked. They were again leak checked in M15. They were then checked for fit over side counters and passed. They were finally cleaned with warm water and simple green. Side pockets were installed and the vacuum chambers were pumped overnight. Then the flanges were leak checked and they passed. System deemed operational.

Author: 
Deepak Vyas