Maintenance for CP-05

Date: 
Wednesday, April 30, 2014
Synopsis: 
Pump serviced
Equipment/Beam Line: 
Description: 

Pump performance was inadequate.  Pump was rebuilt.  A repair kit and Array Kit were changed.  Displacers were cleaned and installed.  New Helium was charged and pump was tested.  Test resulted in 10K temperature and pump was installed in the BNQR Sample space. 

Author: 
Deepak Vyas